Sewer rehabilitation in Saulheim

The impermeability of drainage systems is required for the goals of ‘public health and safety’ and ‘environmental protection’. Building on the sewer rehabilitation strategy and various TV inspections, the Wörrstadt municipal utility company commissioned igr to undertake a detailed planning exercise for sewer rehabilitation. The sewer pipe sections and manholes with damage which required immediate or short term repair were structurally rehabilitated.

Services provided by igr

  • Creation of the rehabilitation strategy
  • Technical rehabilitation planning
  • Tendering and awarding of the contract
  • On-site construction supervision

Key figures

  • 293 rehabilitated sewer pipe sections with a total length of ca. 10.6 km
  • 43 pipe linings with a total length of ca. 1.6 km